Consultant says 75% of concrete done on Adams/Jackson/Cary project; council presses for better resident notices
Summary
A consultant told Lincoln Heights Village Council that concrete work on the Adams, Jackson, McGee and Cary streets-and-sidewalks project is roughly 75% complete, with asphalt remaining and a target finish date of May 29; council and residents pressed for clearer, written communications after access problems this fall.
Danielle Steinhauser, a project consultant, told the Lincoln Heights Village Council on Dec. 8 that about "75% of the concrete work is done" on the Adams, Jackson, McGee and Cary streets-and-sidewalks project and that asphalt paving will be the final step.
Steinhauser said the work on curbs, sidewalks and aprons on the south side of Jackson between Douglas and Cary should be completed that week and — weather permitting — crews would resume concrete work in March on remaining segments. She gave a target completion date of May 29 and said the project is funded from three different sources, without specifying the exact funding mix.
The…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat