Flagstaff Airport outlines TSA checkpoint upgrade, snow‑removal facility timeline and terminal landscaping plan
Summary
Airport staff told commissioners a TSA screening storefront permit is issued and construction is expected to start Jan. 5, 2026 (phase work to keep checkpoint open), the snow‑removal equipment building awaits a possible discretionary FAA determination in January, and terminal landscaping was prioritized by the city's beautification committee for FY27 funding.
Airport staff delivered a package of capital‑project updates at the Dec. 17 commission meeting, detailing a short‑term TSA screening upgrade, a multi‑phase snow‑removal equipment building funded in part by the FAA and a landscaping/wayfinding project prioritized for fiscal 2027.
Adam Miele, airport program manager, said the building permit for the TSA screening storefront has been issued and staff are planning construction to begin Jan. 5, 2026. "This project's broken up into 2 phases," Miele said, explaining the smaller personnel door will be constructed first so the checkpoint can…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat