Flagstaff Airport outlines TSA checkpoint upgrade, snow‑removal facility timeline and terminal landscaping plan

December 22, 2025 | Flagstaff City, Coconino County, Arizona


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Flagstaff Airport outlines TSA checkpoint upgrade, snow‑removal facility timeline and terminal landscaping plan
Airport staff delivered a package of capital‑project updates at the Dec. 17 commission meeting, detailing a short‑term TSA screening upgrade, a multi‑phase snow‑removal equipment building funded in part by the FAA and a landscaping/wayfinding project prioritized for fiscal 2027.

Adam Miele, airport program manager, said the building permit for the TSA screening storefront has been issued and staff are planning construction to begin Jan. 5, 2026. "This project's broken up into 2 phases," Miele said, explaining the smaller personnel door will be constructed first so the checkpoint can continue operating and the larger double door — the main passenger entrance — would follow. He said the current project cost estimate is $69,000 and that construction work will be done during daytime hours.

On the snow‑removal equipment building, staff said FAA funding has covered phases 1 and 2 and that a discretionary phase‑3 grant application (to cover additional design and move the project to a final GMP) was submitted and in final internal review; staff said a determination could come as early as January and that further council approvals will be required before procurement and long‑lead orders.

Staff also previewed a terminal landscaping project that the city's Beautification and Public Arts Committee (VPAC) prioritized for fiscal year 2027. The item will include accessibility upgrades (including a service animal relief area) and wayfinding improvements; staff said they expect to hire a landscape architect and to solicit public feedback once the project enters design.

Operations highlights reported at the meeting: year‑to‑date enplanements and operations figures reflected mixed trends (staff cited temporary impacts from a government shutdown earlier in the year), fuel sales were up roughly 15–16% year‑to‑date and November parking revenue was flat compared with last year while year‑to‑date parking revenue was up about 12%.

At the close of the meeting the commission approved last meeting's minutes by voice vote (motion by Commissioner Nicholas Barraza, second by Commissioner Andrew Schaus). The commission confirmed there will be no meeting in January and reconvened Feb. 12.

No formal votes were taken on the capital projects themselves at this session; staff said expected procurement steps and council referrals will follow as grant decisions are finalized.

View the Full Meeting & All Its Details

This article offers just a summary. Unlock complete video, transcripts, and insights as a Founder Member.

Watch full, unedited meeting videos
Search every word spoken in unlimited transcripts
AI summaries & real-time alerts (all government levels)
Permanent access to expanding government content
Access Full Meeting

30-day money-back guarantee

Sponsors

Proudly supported by sponsors who keep Arizona articles free in 2026

Scribe from Workplace AI
Scribe from Workplace AI