Downtown Courthouse work set to begin; chillers and 4‑pipe conversion move to design and bid phases
Summary
County staff said final color selections were made for a Downtown Courthouse upgrade, a Jan. 8 preconstruction meeting is scheduled and work is planned to start Feb. 2; veil chiller bidding and a four‑pipe conversion orientation were scheduled for February.
Get email alerts on the Facilities Projects topic
No spam. Unsubscribe anytime.
Kurt (Unidentified Speaker 6) told the committee that final color selections for the Downtown Courthouse upgrade were made and that a preconstruction meeting is scheduled for Jan. 8, with construction planned to start Feb. 2. "Were gonna have a pre construction meeting I believe it's on January 8, and they're starting construction on February 2," Kurt said, and added the schedule was coordinated with Lori Wakeman and the judges.
Kurt also said the veil chillers will be advertised to contractors on Feb. 12 and the four‑pipe conversion project has a project orientation meeting on Feb. 24; he noted that the assessor's office project will be scheduled later in the year for the following winter.
Maintenance will begin moving remaining items from the treasurer's old space starting around Jan. 6 in preparation for reconfigurations related to the Downtown Courthouse project. Kurt advised the committee that these dates reflect current planning and that final contractor schedules and procurement steps remain to be completed.