Central Falls committee advances Stage 3 design and expedited demo for dual-language school, keeps April 1 demo target
Summary
The Central Falls School building group approved the Stage 3 design development submittal and an expedited abatement/demolition package for the new dual-language school and the existing Central Falls High School. The committee also reviewed construction progress and set an ambitious April 1 demo start as a working target.
The Central Falls School Building Committee voted to submit Stage 3 design development documents and to advance an expedited early abatement and demolition package for the new dual-language school and the existing Central Falls High School.
Members heard a construction update from Erica, who said the education wing of the new high school is ahead of the community wing and that "we're really starting to gear up on turnover," with owner training and commissioning scheduled to begin in January and furniture, fixtures and equipment arriving in February. Erica reported the project's target for the first day of school is February 23.
Design leads Julie and Justin outlined the schedule for the early demo…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat