Council approved a final change order that reduces the Silvertown Drive waterline and resurfacing contract by $80,625.75 (8.6% under bid). City staff said narrower trenching and milling work saved material and labor, producing significant project savings and no negative impact on the finished work.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Sylvania City Council on Dec. 1 approved a change order that reduces the contract for the Silvertown Drive waterline replacement and resurfacing project by $80,625.75, a reduction staff described as 8.6% under the original bid amount.
Mr. Shaw reported crews replaced about 3,800 feet of 8‑inch waterline and completed resurfacing work. He told council the contractor used a narrower trenching bucket and less base pavement removal than expected, producing notable savings. Mr. Shaw cited roughly $52,000 saved on trench width and about $43,000 of material savings tied to the narrower equipment use; he said OhioX performed the work and produced a quality finished product.
Council introduced and approved Ordinance 137‑2025 as an emergency measure to accept Change Order No. 1 and decrease the contract amount by $80,625.75. Members praised the contractor for the efficient work and authorized final acceptance under the terms presented.