Village Board approves Main Street sidewalk design; retaining-wall and driveway work included

Village Board of East Troy · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved the final design for a 5-foot concrete sidewalk on the south side of Main Street from the square to the Overlook Ridge development, including a plan to incorporate a nearby homeowner’s retaining wall and driveway approach; staff will bring bids and a county right-of-way agreement back for approval.

Jason presented the final design for a 5-foot concrete sidewalk along the south side of Main Street from the square east to the Overlook Ridge development, describing minor property adjustments and two property-owner requests: (1) the village pay to tie into a recently constructed retaining wall (estimated roughly $2,000–$3,000) and (2) replace a removed section of driveway with concrete rather than asphalt to match the homeowner’s planned full-concrete driveway.

Engineers said the alternate driveway work is cost-neutral in the context of the project and the retaining-wall detail is included in the contract drawings. Jason and Tim said they had met with affected property owners and with county right-of-way staff and planned to return with the county agreement and bidding package. A trustee made the motion to approve the design, a second was given, and the motion carried by voice vote.

The board asked staff to include the retaining-wall scope and driveway approach in the bid package, confirm required county approvals, and return with specific bid amounts and funding details before construction begins in 2026.