Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Facilities topic

No spam. Unsubscribe anytime.

Oak Grove board hears construction update; elementary connection to be bid in January

Oak Grove R-VI Board of Education · December 18, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board heard that locker rooms are nearly complete and that a separate 2,000 sq. ft. elementary connection will be bid in January; staff expect an April start and August completion if bids proceed as planned.

District staff told the Oak Grove R-VI Board of Education that construction on auxiliary spaces is nearing completion and that work on an elementary connection has been pulled into a separate bid package.

Staff said locker rooms are nearly finished — lockers are on site, installers are working, and remaining work includes sinks, some toilets, doors and paint. Masonry and exterior block walls were reported as substantially in place. The board was told the elementary connection was split into a stand-alone project to secure dedicated funding; staff reported a pre-bid meeting with five companies and said bids are due in January with a probable April start and an August completion target for the roughly 2,000-square-foot connector.

No formal action was required at the meeting; staff said they will schedule a walkthrough for board members once interior work is complete.