District outlines construction phasing; officials pledge to minimize program disruption
Summary
Construction leaders told the Westonka board that interior phases (classrooms, administration, media center and gym) will be handed over in stages—some during holiday breaks—and staff plan phasing logistics to reduce interruption to recreation programs and community education.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
District construction representatives gave a phased update on the high‑school and campus work and described steps to limit disruption to programs and community users.
The presenter reported Phase 1 (lower‑level math and science) is complete and occupied and that Phase 3 (administration building) steel is erected. Phase 4 handovers for remaining learning spaces are planned over the Christmas break, with interior finishes continuing; later quarters will address the gym, new floor and seating, and exterior work. The presenter said the site will be weather‑tight while interior work continues and emphasized close coordination with building staff on move‑ins.
Board members and staff discussed impacts to community education and summer programming. District staff said pool and WACC access will be limited at times and that adventure club and other summer offerings will be moved to partner sites (Grandview and Our Lady of the Lake) where needed. The district will publish a phasing logistics plan for staff and community that maps site access and timing.
Officials said the work will create a busy summer of activity but emphasized planning to preserve student opportunities and community programs.