Livingston County board approves 18‑month extensions for two solar projects after engineering delays
Summary
The board approved 18‑month extensions for two solar‑farm projects, citing slow reviews from the county's chosen engineering firm (ESI) as the reason for delay; the measure passed on roll call with at least two dissenting votes.
The Livingston County Board on Thursday approved 18‑month extensions for two solar‑farm projects, citing delays in the county engineering review process.
Mike Hague, chair of the county’s Ag & Zoning Committee, told the board both projects — recorded in the meeting as SUDash8Dash22 (BroadLightSolar) and SU‑2‑22 (Blue Stem Solar) — asked for the extensions because the county’s contractor,…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat