USD 4 board hears two‑phase elementary HVAC plan; district says total cost should stay under $6 million
Summary
District projects presenter described a two‑summer HVAC replacement for the elementary school with a construction estimate of about $5.3 million and an operating budget window of $6 million including fees and contingencies; the board plans to consider a GMP in February.
Mister Loomis, the district projects presenter, laid out a two‑phase plan to replace heating, ventilation and air‑conditioning equipment at the elementary school and offered preliminary construction estimates on Dec. 8.
“Phase 1 of this project will be to tackle that section of the building … the classroom wing,” Loomis said, explaining the district plans to replace VRF units for classrooms during summer 2026 and address administrative, music and support spaces in summer 2027 (SEG 138-156; 154-161). He said Universal Construction’s estimate for the two phases is about…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat