Supervisors approve $210,672 pay estimate to contractor for Bradgate tile project

Humboldt County Board of Supervisors · December 29, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved Pay Estimate #1 and a payment of $210,672 to contractor Rob Nisk Weathers (40% complete) for the Bradgate line tile installation; staff said about 2,800 of 6,500 planned feet have been installed.

Humboldt County supervisors approved Pay Estimate #1 to Rob Nisk Weathers for $210,672, representing roughly 40% completion of the Bradgate line tile installation, the board heard.

Staff reported that contractor Colin said work started in early December after a delay and that the contractor had installed about 2,800 feet of the approximately 6,500 feet planned. The project manager told the board the pipe is being installed within design elevation tolerances and that progress is satisfactory despite snowy weather. A motion to approve Pay Estimate #1 was made, seconded and carried by voice vote.

The transcript does not provide the project contract number or detailed pay application line items; the motion approved the pay estimate as presented. Supervisors did not record any dissent on the payment in the excerpt.

Next steps: County staff will process the pay voucher for the contractor and continue monitoring project progress through subsequent pay estimates.