Wellington authorizes property acquisitions for Cleveland Avenue improvements

Wellington Town Board of Trustees · November 19, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board approved Resolution No. 52-2025 allowing staff to acquire multiple properties and temporary construction easements to complete the Cleveland Avenue improvement project, relying in part on roughly $4.44 million in CDOT grants.

The Wellington Board of Trustees on Nov. 18 authorized staff to proceed with right-of-way acquisitions needed for the Cleveland Avenue improvement project.

Public Works Director Bob Dowling told the board the town has secured approximately $4,444,000 in CDOT funding from five sources, executed an IGA with CDOT in 2023, completed 90% design, and advanced appraisals and fair-market-value determinations. Dowling said the town had sent out memoranda of agreement and temporary construction-easement packets; at the time of the presentation two MOAs and corresponding TCEs were signed and additional closings were scheduled.

Dowling asked the board to grant authority to spend in excess of staff-approval limits for two of the purchases and to allow closings consistent with MOAs and CDOT fair-market-value findings. He described a target schedule (advertise contract in January, anticipated construction start in early March and completion in November) and noted grant-spend and close-out deadlines the town must meet.

A trustee moved to pass Resolution No. 52-2025 authorizing staff to acquire the properties; the board approved the resolution by roll call.

The project will proceed through the right-of-way acquisition process and subsequent contract and construction phases; staff said some closings were scheduled two days after the meeting and could be delayed if the board preferred.