Council hears detailed update on sewer project; staff says BlackRock remains on critical path and household hookups unlikely until late spring
Loading...
Summary
City staff told the Bruceville-Eddy council that the wastewater plant and sewer mains remain incomplete: railroad crossings, testing, a missing generator at one lift station, and other outstanding work mean the first household connections are likely "late spring, early summer." The contract lists Dec. 31 as a target and the city may consider remedies if the contractor fails to finish on time.
During the standard-report agenda item, Speaker 9 (role not specified) gave a detailed status update on the town’s sewer and wastewater project, explaining which contractors are responsible for distinct workstreams and what remains to be completed before households can be connected.
Speaker 9 said three of the four lift stations have standby generators installed but the lift station on Hungry Hill Road still lacks an installed generator. On the sewer mains, Speaker 9 said the contractor has installed mains but still must complete railroad crossings and pass pressure and manhole testing before service taps can be connected.
"It's likely to be late spring, early summer before the first toilet is flushed," Speaker 9 said when asked about household hookups. He explained that mains, tested manholes and powered lift stations must all be fully operable before connections are permitted.
Speaker 9 identified BlackRock as the key contractor on the critical path: "The key contractor for this is BlackRock. There's nobody who can finish their work until BlackRock is finished with theirs." He added that the contract currently lists Dec. 31 as the completion date and that the city has provisions to take action under the contract if work is not complete by that date.
Speaker 9 also named other contractors with separate responsibilities: a contractor called Skye Woods is responsible for installing service lines that connect to the BlackRock sewer main, another team is responsible for lift stations, and another for the wastewater treatment plant on city land. He emphasized that each contractor’s schedule is interdependent.
What happens next: Staff said they anticipate continued testing and staged connections; council members will consider the contractor’s request for additional time and potential contractual remedies if the December deadline is missed. The transcript records discussion of the delay and the city’s options but does not show a council decision on remedies during this meeting.

