County engineer reports 2025 construction season under budget by about $1.2 million

Bremer County Board of Supervisors · December 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Bremer County's engineer reported final construction costs for bridges and paving were below budget: combined projects budgeted about $6.2 million with spending just over $5.0 million; board asked for lifecycle and deficient-bridge analyses to inform future budgeting.

Bremer County's county engineer presented a final report on 2025 construction-season projects and told the board the county finished the season under budget by roughly $1.2 million.

Landon said Bridge 1114 had a budget of about $1.6 million, with a final cost of roughly $1,218,000 (savings of about $381,000). Bridge 1115 was budgeted at $900,000 with final costs just under $606,000 (savings of about $294,000). Paving projects on County Road C33 were budgeted at about $2.7 million and finished at approximately $2,617,000 after change orders and shoulder widening. Landon also reported another joint bridge project budgeted at $1,000,000 with a total cost of about $1,212,000; the county's share is roughly half for that joint work with Chickasaw County.

Overall, Landon said the aggregate budgeted amount for the listed projects was about $6.2 million and total spending was just over $5.0 million. He told supervisors the savings are positive but also affect long-term planning because unspent budgeted dollars could have been allocated elsewhere. Supervisors asked for a reanalysis of deficient/poor bridges and a lifecycle cost report for recently resurfaced roads (for example, Shelby Ridge repave cost about $376,940 and an expected 25-year life cycle was cited).

Landon also noted a recent truck incident while clearing roads in heavy snow; the vehicle sustained frame damage and was submitted to insurance, with cost assessment pending. The driver was shaken but uninjured.

The board asked staff to prepare a short report on deficient bridges and lifecycle costs to inform budgeting for future seasons.