The board approved an informational amendment increasing a drainage project from $450,000 to $520,000 (adding $70,000 for an additional culvert) and set a public hearing for landowners on Jan. 6 at 09:00 to review revised costs.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
The supervisors approved an amendment to a joint drainage district project that increases the previously approved cost and schedules a public hearing for affected landowners.
Staff said the amendment adds $70,000 to the earlier approved $450,000 total for the project (bringing the new total to $520,000) to cover an added culvert and that landowners will be asked to review the amended report prior to the January 6 public hearing at 09:00. The amendment is informational and will be posted on the county website for landowner review before the hearing.
A motion to approve the amendment was made, seconded, and carried with recorded 'aye' votes from the board. The board also approved a low‑cost repair request for DD 35 Main ditch — estimated at less than $1,500 — to hire a contractor with a long‑reach machine to remove a dump in the dam; that action was moved and approved during the same meeting.
The drainage amendment will proceed to the scheduled public hearing for landowner input as required by drainage‑district procedures; no final levy or assessment was decided at the meeting.