Parish hears $42,129.49 change order for Henderson water control work and $1.23 million drainage contract award

Saint Martin Parish Government · December 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Officials discussed a $42,129.49 change order and nine-day extension for Henderson Water Control Structure repairs and moved to award a $1,227,872 contract for Cypress Island/Joe Bay drainage maintenance phase 2 to the low bidder; no recorded final vote is in the transcript.

The parish discussed two infrastructure items: a change order for underwater repairs at the Henderson Water Control Structure and a bid award for the Cypress Island/Joe Bay drainage maintenance project.

A staff presenter described change order No. 1 for the Henderson Water Control Structure repairs by Reliance Industrial Solutions LLC: a $42,129.49 contract increase and a nine-day time extension. The change order was attributed to additional damage discovered once water levels were lowered for underwater assessment. "This is the the reason for the $42,000," the presenter said, adding that concrete pours and steel-plate installation are upcoming work items; the speaker also said the project remains within the original overall budget target.

Separately, the council reviewed a resolution to award the Cypress Island/Joe Bay drainage System Maintenance Project (phase 2) to low bidder Down South Construction Services LLC for $1,227,872. Staff reported the bid came in well under budget and said they were "very pleased" with the result.

The meeting record includes these requests for council consideration; the transcript does not record final vote tallies or a formal roll-call outcome for either item. Staff noted the Henderson work is tied to water-level conditions and that steel and other materials have been purchased and staged to resume work when conditions permit.