Commission approves $48,000 to continue county parking-ramp rehabilitation
Summary
Following a Walker Consultants assessment and completion of Phase 1 using ARPA funds, the commission approved a $48,000 budget amendment to pay professional services for Phase 2 of the county parking-ramp rehabilitation.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
County staff briefed commissioners on results of a Walker Consultants structural and condition assessment of the county parking ramp. Phase 1, described as the most urgent work, has been completed using ARPA funds. Staff requested a $48,000 budget amendment from parking-ramp maintenance to pay for professional services required to proceed with Phase 2 repairs that were not eligible to be paid directly from ARPA due to federal procurement rules.
Commissioners asked about the parking fund balance and the likely scope of Phase 2 work (door replacement for stair towers, targeted concrete repairs and perimeter handrail work). Staff confirmed Phase 2 would draw on remaining ARPA-eligible construction funds for the capital work but that the professional-services payment must come from the parking fund. The commission approved the $48,000 amendment by voice vote.
Staff said they will pursue the Phase 2 repairs identified in the Walker study until available funds are expended.