Commissioners discuss airport repairs, disputed contractor change orders and authorize payment of several small invoices
Summary
Officials and attendees debated responsibility for storm-damaged airport repairs and disputed change-order invoices from a contractor; commissioners authorized payment of three smaller contractor invoices while the larger change-order dispute remained unresolved.
Get email alerts on the Airport Contract Dispute topic
No spam. Unsubscribe anytime.
Madison County commissioners spent an extended portion of the meeting on airport repair work, contractor change orders and payment disputes after storm-related damage.
A speaker described drainage, grading and concrete work completed by local contractors to repair hangars and other airport facilities. The county has a disputed set of change orders from a prior contractor (identified in the transcript as SERVPRO and, elsewhere, a similarly spelled contractor name) for below-grade items the insurer would not cover. The speaker said the county hired other contractors to correct alleged deficiencies and that the county has not paid some of those smaller corrective invoices.
Commissioners and staff discussed options for resolving the dispute: require original invoices and documentation, send a reduced payment to the larger contractor and mark it payment in full, or pay third-party contractors now and recover differences later. One participant described a proposal to send a check to the larger contractor 'minus the difference' and label it 'payment in full' to close matters if necessary.
The board then moved to authorize specific, smaller payments for completed corrective work: invoice 2025166 to Weisenberger Builders for $4,000; a Murphy Trucking invoice for $1,577; and invoice 836509 to Nguyen Francis for $827.45. The motion was seconded and approved by roll call.
Commissioners also discussed whether the airport board had formally authorized the out-of-scope repairs and whether payment should be withheld pending written confirmation from insurer representatives or a structural engineer. Participants asked staff to collect original invoices, change-order documentation and any written promises from the larger contractor or insurer. The board instructed staff to proceed with the three small payments approved in the meeting and to continue negotiations or claims work on the larger disputed claim.
Why it matters: the discussion affects how the county resolves disputed contractor work and whether it must absorb additional repair costs; it also affects tenants at the airport who have delayed moving back into repaired hangars.
What’s next: staff will send the requested paperwork, pursue clarification with the insurer and contractor, and report back to the commissioners on options for settlement or offset.