Val Verde County ratifies $2.3 million federal award for target-range construction, notes shortfall against contract

Val Verde County Commissioners Court · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The court ratified acceptance of a $2,316,420 federal award for the Robert E. County Target Range Facility; the total contract price cited was $3,028,000 and commissioners discussed gap‑closing through prior borrowing and additional funding.

Val Verde County Commissioners on Jan. 4 ratified acceptance of a $2,316,420 federal award to construct the Robert E. County Target Range Facility.

Why it matters: The grant restores a large portion of previously identified funding for a county shooting range project and allows the county to pursue finishing interior work that had been planned as a later phase. County staff said the project contract is approximately $3,028,000; with the grant and previous borrowing the county expects to be able to complete the facility though some interior work will be rebid to control costs.

What happened: County staff and the judge explained that the new federal award is entirely new funding, not a reallocation of earlier dollars. Commissioners voted 5‑0 to ratify acceptance of the award. The judge and staff said the county previously borrowed funds for related projects and still had roughly $761,256 in net available funds after accounting for earlier allocations and new grant money.

What’s next: The court instructed staff to proceed with procurement steps; an item later on the agenda was scheduled to reopen bids or solicit pricing for interior partitions and finishes to determine whether contractors could complete the inside within budget.

Quote: Judge Valdez: “Good news is that we did receive $2,316,420… Bad news is the contract was $3,028,000 to build it.”

Provenance: Item 14 discussion and vote to ratify acceptance of the federal award.