Summary

Freeman Construction presented a guaranteed maximum price for the new Whites Park show barn reported as under budget; court approved the GMP and also authorized an RFP for a speed-control office expansion expected to exceed procurement limits.

Chambers County’s Commissioners Court approved a guaranteed maximum price (GMP) for a new Whites Park show barn and authorized staff to issue a request for proposals (RFP) for a speed-control office expansion.

Mike, representing Freeman Construction Administration, presented the GMP for the show barn and told the court the combined construction and architectural fees were under budget. Commissioners praised the work and approved moving forward after a motion was made and seconded.

On a separate item, staff recommended issuing an RFP for the speed-control office expansion after amending the narrative and identifying that the project would likely exceed procurement limits for a simple bid. The court approved proceeding with an RFP.