DeKalb County to lift SurfNet stop-work order if company provides enforceable removal letter
Summary
After highway staff reported improperly installed conduit, commissioners agreed to release a stop-work order for SurfNet provided the company submits an updated letter acknowledging removal obligations and an agreed completion deadline; the county emphasized reliance on the company's bond if work is not completed.
Get email alerts on the Infrastructure Contractor Compliance topic
No spam. Unsubscribe anytime.
DeKalb County commissioners agreed Dec. 8 to allow highway staff to release a stop-work order on SurfNet work if SurfNet provides an updated letter containing language recommended by county counsel and a firm completion date.
Highway staff said crews for SurfNet had resumed work after the county issued a stop-work order because conduit was installed too shallow and too close to the road. A county official said SurfNet proposed removing the improperly placed conduit when weather allows; in response, county counsel recommended adding explicit promises about the county's ability to rely on the letter and proposed a specific deadline. "We have a $100,000 bond on them," a highway official said, noting the bond gives the county enforcement leverage if SurfNet fails to remove the conduit.
Commissioners discussed adding a deadline to the company's letter (options discussed included May 1 or May 22, 2026) and using a stop-work order if SurfNet fails to complete removal by that date. One commissioner said a written letter alone might be argued as a nonbinding promise, but counsel said a revised letter plus the county bond makes enforcement more practical.
The commission voted to permit the highway director to release the stop-work order conditioned on receipt of an updated SurfNet letter with counsel's additional language and an agreed completion deadline.
Why it matters: County roads and right-of-way safety can be affected by shallow or incorrect conduit installations. Staff balanced the need to enforce standards against residents' connectivity needs and SurfNet's grant deadlines.
Next steps: County counsel will provide suggested language for SurfNet's letter; SurfNet must deliver an updated letter acceptable to counsel for the stop-work order to be lifted, and the county will use bond or stop-work authority if the company fails to meet the deadline.