Bonneville County discusses Iona Road change order; reimbursement expected from sewer district
Summary
County staff presented Change Order No. 1 for the Iona Road widening project, described it as a pass-through cost under the county contract with HK, and said Bonneville Sewer District will reimburse the county; a motion to approve the change order was made but no vote tally was recorded.
Bonneville County commissioners reviewed Change Order No. 1 for the Iona Road widening project and were told the cost is a pass-through under the county’s contract with HK.
Speaker 1 said the county must process the change order because HK performs the work through the county contract, but that "we…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat