Residents ask Scott County to press Army Corps and state agencies as Cove Creek erosion threatens homes
Summary
Multiple Cove Creek residents told supervisors that recent flooding and channel changes have eroded yards, damaged outbuildings and made county roads impassable; residents urged letters and agency intervention, and staff said they will follow up with NRCS, Army Corps, FEMA and state agencies.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Residents from the Cove Creek area described extensive channel erosion and property damage to the Board of Supervisors and asked the county to help secure federal or state assistance.
“My creek channel there is completely filled… the next high water event could possibly take out homes and structures,” Myron Fields told the board, listing properties that have lost 20–75 feet of bank and describing recent gullying of county roads. Greg Johnson, who said he is familiar with the creek’s lower reaches, reported similar bank loss and warned that the channel’s current path threatens a ford crossing and utility access.
Fields said he had contacted the Army Corps of Engineers, FEMA, and the offices of regional representatives without decisive action; he also said Lenowisco and the health district were aware and that Lenowisco had shared family survey data with the Virginia Cancer Registry for a separate public-health matter. Residents asked the board to send letters to the Corps, DEQ, NRCS and others and to press for an environmental review if a federal project were approved.
County staff said there is a meeting scheduled with state officials about winter‑storm priorities and that NRCS had walked several sites to consider program eligibility; the board agreed to draft and send letters to multiple agencies and requested staff follow up with the contact the residents provided to Lenowisco.
No immediate county construction work or emergency funding was approved at the meeting; supervisors said they would continue coordinating with state and federal agencies and evaluate next steps once agencies respond.