Commissioners move to set hearing after staff find $1.2 million construction‑program gap

Mason County Commissioners briefing · December 25, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff told commissioners the county’s adopted budget lists $11.4 million while the annual construction/6‑year program lists $12.6 million, leaving a $1.2 million discrepancy; staff proposed setting a hearing to amend the program and defer lower‑priority road fund projects to reconcile the difference.

County staff informed commissioners that a discrepancy exists between the adopted budget and the annual construction/6‑year transportation program: the budget lists $11,400,000 while the construction program lists $12,600,000, creating a $1,200,000 gap.

Unidentified Speaker 7 (staff) said the difference must be reconciled so the county’s certificate of good compliance and related reports are accurate. Staff explained that the $1.2 million gap primarily affects road‑fund match dollars: the county currently shows $2,400,000 in road fund money intended to match about $10,000,000 in grant funds and would need to reduce the road‑fund portion by $1,200,000 unless the budget is adjusted.

Speaker 7 outlined an administrative approach: set a hearing to amend the annual construction program now (to correct the delinquency with the state) and revisit budget amendments in April if commissioners want to restore projects later. "It's got to be road fund money because with grant money ... it balances out," Speaker 7 said.

Staff identified a set of lower‑priority or placeholder projects that could be removed from the annual program to meet the required number of projects — noting the list would shrink from roughly 25–27 projects to about nine — and recommended the commission authorize a hearing and subsequent advertisement. Commissioners asked staff to show a prioritized list with ballpark costs and to schedule the hearing promptly to avoid missing reporting deadlines.

No formal vote was recorded at the briefing; staff will prepare the hearing notice, a prioritized project list, and an explanatory briefing on tradeoffs and potential impacts to grant projects.