Bridge change order approved and Rapidan Dam update shows $11.5M funding gap

Blue Earth County Board of Commissioners · January 6, 2026

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a $103,902.96 change order for State Project 007609015 (CSH 9 bridge design). Staff updated the board on Rapidan Dam and the County State Highway 9 bridge, reporting a $33.8M estimated total cost versus $22.3M currently allocated, leaving an $11.5M shortfall and noting FHWA requested a 90% cost estimate to consider additional funding.

The board approved change order number 1 for State Project 007609015, the design contract for the County State Highway 9 bridge over the Plymouth River. Staff explained TKDA is the prime consultant and Braun Intertech performed geotechnical work; additional services were required for access assistance, deeper borings after substructure revisions, and revised foundation recommendations. The approved change order amount is $103,902.96.

In a related presentation, staff provided a detailed update on the larger County State Highway 9 bridge replacement and Rapidan Dam efforts: 60% plans have been submitted to MnDOT, updated cost estimates include an 18% contingency, and the current combined federal and state funding allocated is $22,300,000. Staff reported an anticipated total project cost (including design and contingencies) of $33,800,000, producing an estimated funding gap of $11,500,000. Staff said the Federal Highway Administration wants to see a 90% cost estimate to reduce contingency assumptions before FHWA will consider additional funding requests if project costs exceed 20% above current allocations.

Board members received the update and approved the change order by voice vote; staff said they will continue coordinating with MnDOT and FHWA on potential additional funding paths and next steps.