Kiski Area SD hears construction progress, reviews $44,000 change order and two curb-replacement options
Summary
Contractor update showed steady progress on the intermediate school; board reviewed change order 12 (~$44,000) covering 10 field-condition items and debated two curb-replacement options (partial ~$27,270 or full replacement ~$69,000) to place on the upcoming voting agenda.
Mister Dave of the project contractor gave the Kiski Area School District board a month-by-month progress report on the intermediate school, saying Area A classrooms are painted and ceiling-gridded, Area B drywall and kitchen work are nearly complete and Area C (gym and shops) continues to advance. "Like I said, it was a good month," he told the board, noting that rooftop units are scheduled to be set next week and some windows were delayed roughly a week and a half.
The contractor described change order 12 as 10 discrete items — roofing insulation adjustments related to field conditions, custom anodized paint on two aluminum storefront doors, materials to mount…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat