Intermediate school renovation 50% reroofed; board reviews several change orders and technology add-ons
Summary
Contractors reported progress on drywall, painting, mechanical work and roof replacement at the intermediate school and described change orders including a plumbing reroute and added data/wireless outlets; access-control add‑ons were discussed but not voted on at the meeting.
KISKI AREA SD — Contractors told the board June 11 that the intermediate school renovation is advancing on multiple fronts: drywall finishing and painting are underway in classroom areas, ceramic tile deliveries are ready for bathrooms, mechanical and electrical rough‑ins continue, and the reroof is approximately 50% complete.
A construction representative said crews have poured the kitchen slab, started CMU block walls for the kitchen, and are preparing for rooftop-unit installation in August or September. "I would guess they're about…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat