Marshall County jail project update: staff seek $48,434 change order for additional cameras
Summary
County project staff reported the jail construction is about 24% complete and requested a $48,434.35 change order to add nine security cameras and tablets; staff said two locations may require wall modifications and any extra cost would come from contingency.
Marshall County employees gave the commission a construction update for the new county jail on Nov. 12 and asked the commission to consider a change order to upgrade the facility’s camera system.
Kelly Howard, who presented the project update, reported the work is about 24% complete and that masonry, mechanical, electrical and plumbing…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat