Kiski Area SD board hears intermediate school construction progress, pending change orders and disclosure of related litigation review

Kiski Area School District Board of Education · September 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Superintendent Dr. Lohr and a contractor updated the board on the intermediate school renovation: classrooms and gym near finishing stages, multiple site-related change orders are on the agenda, and the district disclosed an executive session about potential construction litigation.

Dr. Lohr, superintendent of Kiski Area School District, opened the construction update Tuesday night, saying the district is continuing to press the general contractor for an action plan to meet the project completion date.

Dave, a construction representative from PJ (contractor identified in the meeting), described work across three zones: Area A classrooms have ceiling grid, painting and markerboards installed and casework scheduled; Area B shows drywall and masonry infill with kitchen ductwork and hood complete; Area C (gym and TechEd) requires only painting and floor refinishing after near-complete ductwork. He noted delivered items on-site including bleachers and lockers and said ceiling tile delivery and final mechanical work were imminent.

The board was told a change-order packet for Lyakaris Construction will be on the meeting agenda; Dr. Lohr said the items primarily cover recent site concrete, a minor fence revision by the pond and the addition of a painted crosswalk in the new parking lot. "That's what's on the agenda for approval," he said, and invited board questions on the change-order narrative.

Board members also heard that the district is still waiting for a formal action plan from the general contractor to keep the schedule on track. Solicitor remarks later in the meeting disclosed that the board held an executive session earlier to discuss potential litigation related to the construction project referenced in the update.

No formal vote on the change orders or contract was recorded in the public portion of the meeting; the superintendent told the board staff will continue to pursue scheduling and funding details and will bring specific contract items back for formal board action as required.

The board also received a public notice that two firms responding to a guaranteed energy savings project (GESA) questionnaire will present to the public on Sept. 17.