City updates: wastewater upgrades, Mill Street storage building, and County Road 606 relocation
Summary
Staff reported wastewater treatment plant equipment is expected this summer following long lead times and an ADEM funding drawdown; a Mill Street storage building slab and erection are expected in the next 30–60 days; County Road 606 relocation for an FAA-runway extension remains on schedule with FAA funding covering 97.5%.
City staff provided updates on several capital projects. Speaker 3 said the wastewater treatment plant contractor is on schedule and waiting on long-lead screens and equipment ordered earlier; installation is expected this summer and the city has completed an initial…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat