Board hears historic courthouse bid shortfall; contractor selection pushed to Jan. 21
Summary
County staff said three bids were returned for the historic courthouse renovations, with the low bid at about $1.88 million and potential additional costs from a window subcontractor possibly creating a $383,000 funding gap; staff will return with the contract on Jan. 21 for board action.
Get email alerts on the Historic Courthouse topic
No spam. Unsubscribe anytime.
Fluvanna County staff told the board on Jan. 7 that three bids were received for the historic courthouse renovation, with the apparent low bidder at $1,879,000 and higher bids up to roughly $2.5 million. The county has combined county and state grant funds totaling about $2.1 million available and has expended approximately $408,000 to date on prior phases and design work.
County staff said subcontracts for certain specialized work (notably window work) produced price variance; staff is negotiating revised subcontractor pricing with the selected general contractor. "We've received a little over $2,100,000 as a combination of board funds and state funds," the County Administrator said, and explained that selecting a different proposed window subcontractor could add up to about $150,000 in worst-case added costs. Staff estimated an additional $383,000 would be needed to move the project forward given current contingencies, and a 7.5% contingency could raise the potential additional amount to about $530,000.
Board members expressed concern about escalating construction costs, potential delays that risk grant expiration, and the difficulty of value engineering on a historic rehabilitation. Staff said the contract is expected to be presented to the board on Jan. 21, with roof-related work and slates already ordered so that early work can proceed if the contract is approved.
No appropriation was made on Jan. 7; staff requested guidance and will return with final contract documents, subcontractor clarifications and any request for additional appropriation when the contract is placed on the Jan. 21 agenda.