Pac West annex change orders deferred to Jan. 20 as commissioners request itemized costs

Valley County Board of County Commissioners · January 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Pac West and county staff reviewed annex change orders including exit lights required by code, parking striping and low‑voltage work; commissioners asked for detailed hours/mileage and time records and voted to table the item to Jan. 20 at 09:05 for further review.

County staff and Pac West representatives reviewed multiple change orders for the annex project, including exit lights required by the Cascade building inspector, parking‑lot striping and low‑voltage wiring. Commissioners questioned why some items were not in the original contract and why the contractor submitted change orders late in the process.

Terry and other county staff said some items—exit lights and low‑voltage—were either code required or requested by internal staff; Pac West’s project superintendent, Mike Irwin, and the contractor’s representatives said delayed starts and permitting pushed the schedule and incurred costs. Commissioners asked the contractor to provide a detailed breakdown of supervision hours, vehicle expense and day‑by‑day time impacts to verify charges and to separate contractor‑caused delays from work that arose from incomplete plans or permitting.

Because the packet deadline precluded readying all documentation, a commissioner moved to table the Pacific West annex change orders to 09:05 on Tuesday, Jan. 20. The board voted in favor of tabling the item so the contractor can return with detailed time and cost backup.

Next steps: Pac West to supply an itemized breakdown of supervision hours, vehicle mileage/expense and documentation showing which costs resulted from city permitting delays versus contractor actions. County staff will reintroduce the change order request on Jan. 20 after review.