Pasco County updates board on stormwater projects; SWFWMD withdraws cooperative funding for southern outfall
Summary
Pasco County Public Works briefed the MPO on stormwater capital projects: the Hudson/Wildwood trailer-park effort is stalled over easements, the northern outfall is nearing completion this spring, and SWFWMD withdrew cooperative funding for the southern outfall after a third-party review found limited regional benefit.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
Pasco County Public Works engineering manager Chris Hanning presented updates on several stormwater capital projects affecting areas near US 19 and Hudson.
Hanning said the Hudson Stormwater/Wildwood Trailer Park concept study ran into uncooperative property owners and easement obstacles that stalled design work. Staff discussed coordinating with FDOT to install pipes under US 19 during resurfacing projects to reduce costs and improve drainage toward the Gulf.
Construction on the northern outfall is underway; Hanning said East-side work is complete and the pedestrian bridge on the west side of US 19 is expected to be finished this spring. The southern outfall, which had been part of a combined alternative, lost cooperative funding after the Southwest Florida Water Management District (SWFWMD) determined it did not provide sufficient regional benefit following third-party review. Board members urged staff to re-engage SWFWMD, FDOT and local stakeholders to explore cleaning ponds and alternative conveyance approaches that might restore benefits.
Why it matters: Stormwater infrastructure affects flooding and resiliency in low-lying communities; changes to cooperative funding and permitting can alter project feasibility and timelines.
What’s next: Staff will reconvene with SWFWMD, FDOT and local stakeholders to explore options for the southern outfall and pursue coordination opportunities to install pipes during FDOT resurfacing where possible.