Highway department says office project nearly complete; commissioners press final punch-list items
Summary
Highway staff reported the new office and shop are near completion: gas-meter installation, fiber-optic feed, generator backfeeds and sitework are nearly done; commissioners raised guttering, gate and fencing items and asked for careful reconciliation of change-order credits.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Highway department staff reported the new highway office and mechanic shop are approaching completion. The presenter said final plumbing and electrical work remains, a gas meter is scheduled for installation, fiber-optic service will be spliced and connected, and generator backfeeds and security lighting are being finalized. Sitework — binder blacktop, stone for entrances and shaping the back entrance to Lake Salinda Road — is progressing.
Commissioners and staff discussed practical final items: the absence of guttering on the building’s north side and the potential for ice to create hazards in truck bays, the need to add truck-heater receptacles, the installation of a gate and fence on the property perimeter, and ensuring transfer switches and alternate power coordination. The presenter said some credits and change-of-scope items were sent for review and emphasized reconciling those credits under the BOT agreement so the county is not surprised by final costs.
Action: No formal board votes were recorded on change orders at this meeting. Staff indicated they would meet after the session to review the change-of-scope spreadsheet and finalize credits and debits before closing the project.