Staff reports ZSFG Building 5 tendon damage will push 2016 PHS bond projects into early 2026

Citizens General Obligation Bond Oversight Committee · December 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Public Works told the Citizens GO Bond Oversight Committee that post‑tension tendon damage at Zuckerberg San Francisco General’s Building 5 will delay parts of the 2016 Public Health & Safety bond program into early 2026; the contractor is responsible and the city intends to assess liquidated damages.

The Citizens General Obligation Bond Oversight Committee on Dec. 8 received an annual update on the 2016 Public Health & Safety (PHS) general obligation bond, including a construction delay at Zuckerberg San Francisco General (ZSFG) Building 5.

Joe Chin of Public Works told the committee the bond program was originally authorized at $350,000,000 and now shows a revised total of $364,000,000 after about $14,000,000 in bond interest earnings were appropriated. "This bond program was approved for a total bond authorization amount of $350,000,000," Chin said, and he provided line‑item allocations for the six program components.

Chin said three of the six components have been completed and moved into closeout, but ZSFG Building 5…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans