Votes at a glance: SFPUC Dec. 9 meeting — minutes, rules, easements and contingency increases

San Francisco Public Utilities Commission · December 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The SFPUC approved meeting minutes, adopted hydrant-use rules, authorized real-estate agreements with Daly City, approved three Lower Alameda easements, and authorized contingency increases for two contracts; roll-call tallies were recorded for each action.

At its Dec. 9 meeting, the San Francisco Public Utilities Commission recorded the following formal outcomes:

- Approval of minutes (Item 3): Motion by Commissioner Stacy; second by Vice President Leverone. Vote: Arce, Leverone, Jamdar, Stacy — Aye. Item passed; Commissioner Thurlow excused.

- Consent calendar (Item 7): Approved by roll call (Arce, Leverone, Jamdar, Stacy — Aye).

- Hydrant use rules (Item 8): Adopted as amended; required meters/backflow prevention and limited revocable permits to six months. Vote: unanimous among present commissioners (Thurlow excused).

- Daly City real estate agreements (Item 9): Commission approved quitclaim of tunnel easements, conveyance of new easements and a 50‑year license for the inlet pipeline; Daly City will pay appraised fair market value. Vote: Arce, Leverone, Jamdar, Stacy — Aye.

- Easement acquisitions for Lower Alameda auxiliary sewer (Items 10–12): The Commission individually approved negotiated purchase-and-sale agreements and easement deeds for subsurface tunnel rights beneath 491, 495 and 499 Gavin Street. Votes: each item approved by roll call (four ayes; Thurlow excused).

- Contract contingency increases (Item 13): Approved an additional $500,000 cost contingency and a 910-calendar-day duration contingency for the Alameda Creek Watershed Center contract to complete exhibits and address leaks and a two-year maintenance period. Vote: Arce stepped away; remaining commissioners voted Aye; item passed.

- Contract contingency increases (Item 14): Approved $1,000,000 increase to cost contingency and 382-calendar-day duration extension for O'Shaughnessy Dam drainage contract to address site conditions and worker-safety schedule requirements. Vote: unanimous among present commissioners (Thurlow excused).

Ending: Several items will require follow-up implementation steps (permit updates, conveyance documents, contract closeouts) and staff committed to reporting back where required.