The SFPUC approved meeting minutes, adopted hydrant-use rules, authorized real-estate agreements with Daly City, approved three Lower Alameda easements, and authorized contingency increases for two contracts; roll-call tallies were recorded for each action.
Get email alerts on the Meeting Votes topic
No spam. Unsubscribe anytime.
At its Dec. 9 meeting, the San Francisco Public Utilities Commission recorded the following formal outcomes:
- Approval of minutes (Item 3): Motion by Commissioner Stacy; second by Vice President Leverone. Vote: Arce, Leverone, Jamdar, Stacy — Aye. Item passed; Commissioner Thurlow excused.
- Consent calendar (Item 7): Approved by roll call (Arce, Leverone, Jamdar, Stacy — Aye).
- Hydrant use rules (Item 8): Adopted as amended; required meters/backflow prevention and limited revocable permits to six months. Vote: unanimous among present commissioners (Thurlow excused).
- Daly City real estate agreements (Item 9): Commission approved quitclaim of tunnel easements, conveyance of new easements and a 50‑year license for the inlet pipeline; Daly City will pay appraised fair market value. Vote: Arce, Leverone, Jamdar, Stacy — Aye.
- Easement acquisitions for Lower Alameda auxiliary sewer (Items 10–12): The Commission individually approved negotiated purchase-and-sale agreements and easement deeds for subsurface tunnel rights beneath 491, 495 and 499 Gavin Street. Votes: each item approved by roll call (four ayes; Thurlow excused).
- Contract contingency increases (Item 13): Approved an additional $500,000 cost contingency and a 910-calendar-day duration contingency for the Alameda Creek Watershed Center contract to complete exhibits and address leaks and a two-year maintenance period. Vote: Arce stepped away; remaining commissioners voted Aye; item passed.
- Contract contingency increases (Item 14): Approved $1,000,000 increase to cost contingency and 382-calendar-day duration extension for O'Shaughnessy Dam drainage contract to address site conditions and worker-safety schedule requirements. Vote: unanimous among present commissioners (Thurlow excused).
Ending: Several items will require follow-up implementation steps (permit updates, conveyance documents, contract closeouts) and staff committed to reporting back where required.