City, county and Saint Mary's outline Navigation Center/Pathways timeline and funding shortfall; council seeks accountability
Summary
Stockton staff and Saint Mary's updated council on the Zider Navigation Center and Pathways campus construction and operations: construction delays have pushed openings into August–October 2025, total construction investment cited at ~$28.2M and recurring operating revenues fall short of projected expenses by about $3M annually, prompting council calls for metrics and contingency plans.
Get email alerts on the Homelessness Services topic
No spam. Unsubscribe anytime.
City economic development staff and Saint Mary's leadership delivered an extended update July 28 on the Zider Navigation Center and the Pathways facility, projects the city and county moved to stand up after Stockton Shelter scaled back operations.
Tina McCarty (Economic Development) reviewed the multi-year history, construction delays (storm damage in 2023, elevator and door part delays), and staff intervention in construction oversight. Saint Mary's representatives said the navigation center family facility will provide 68 beds; Pathways (pre-fab modules) is expected to be permitted and opened by October. McCarty summarized total construction contributions at roughly $28.2 million (city $7.7M; county/partners ~$20.5M) and said annual campus operational investment (city + county + partners) approaches $17.9M. Saint Mary's presented an annual budget showing revenues around $12M and expenditures near $15M, creating an estimated ongoing $3M shortfall.
Council members repeatedly pressed for transparency and outcomes metrics: how many people exit to permanent housing, family bed capacity, and policies on pets (navigation center currently not allowing pets; Pathways will allow some pet accommodation). Public commenters and council members urged more complete reporting and questioned changes to earlier bed-count projections (initially higher bed estimates were revised as furnishing and safety requirements were clarified).
No formal council action was requested at the meeting; staff said a detailed action plan and an HAP 6 joint application with the county will return for council consideration on Aug. 12. Saint Mary's CEO committed to regular reporting, and councilmembers emphasized the need to show measurable exits from homelessness to justify future funding.