The Lake County Board of Commissioners unanimously approved multiple resolutions including a $20,000 retainage release and acceptance of a $573,985.38 maintenance bond for the Bennett Road sewer project, several HUD-related grant agreements and $13,152,331.87 in purchase orders.
Get email alerts on the County Finance And Procurement topic
No spam. Unsubscribe anytime.
The Lake County Board of Commissioners unanimously approved a package of resolutions at its regular meeting, clearing payments and grant agreements across utilities, housing and county operations.
The board voted to release $20,000 in retainage to J.S. Bovla Excavating LLC and to accept a three-year maintenance bond of $573,985.38 for the Bennett Road trunk sewer improvements project (project 454S2021), according to the utilities presentation. Commissioners McIntosh, Plecnik and Beveridge voted in favor.
Separately, the commissioners authorized execution of FY2025 agreements for Community Development Block Grant funds and Home Investment Partnership (HOME) program funds, and approved agreements under the HOME-ARP (American Rescue Plan) funding stream. Each resolution was moved, seconded and approved by roll call.
The board also approved pay application no. 8 and release of retainage of $382,724.85 to Train Partners US Incorporated for the Lake County Buildings and Grounds HVAC improvements project and authorized purchase orders totaling $13,152,331.87 listed in the commissioner's purchase order approval journal.
Budget adjustments clearing increases and decreases across general and non-general fund accounts, and transfers of cash and appropriations between funds, were approved by unanimous roll call votes.
Votes at a glance - Release retainage and accept maintenance bond for Bennett Road sewer (project 454S2021): Approved; yes 3, no 0. - Certify unpaid water and sewer sums to the county auditor: Approved; yes 3, no 0. - Execute FY2025 CDBG agreements: Approved; yes 3, no 0. - Execute FY2025 HOME program agreements: Approved; yes 3, no 0. - Execute FY2025 HOME-ARP agreements: Approved; yes 3, no 0. - Pay application no. 8 for HVAC project (Train Partners US Inc.): Approved; yes 3, no 0. - Purchase orders totaling $13,152,331.87: Approved; yes 3, no 0. - Adjust appropriations: Approved; yes 3, no 0. - Transfer cash and appropriations: Approved; yes 3, no 0.
What happens next Most actions are administrative authorizations that enable payments, contract administration and program execution. The utilities department indicated it will continue work tied to the Bennett Road project and monitor contract and bond requirements; departments will implement approved agreements and purchase orders according to departmental processes.