Newton County approves $1.5035 million GMP amendment for Factory Shoals Park construction
Summary
The board approved Amendment No. 1 to Sunbelt Builders' contract setting a guaranteed maximum price of $1,503,500 (including pre-construction fees) to move Factory Shoals Park into construction.
Get email alerts on the Parks Capital Projects topic
No spam. Unsubscribe anytime.
Sunbelt Builders representatives asked the Newton County Board of Commissioners on Jan. 6 to approve Amendment No. 1 to the company's contract for Factory Shoals Park, setting a guaranteed maximum price (GMP) to allow the county to move into construction. The board approved the amendment.
Jeff Bryan presented the amendment, saying the GMP being proposed for construction is $1,500,000 and that the contract includes a prior $3,500 pre-construction services fee. He said the design team and staff had determined the best use of the funded amount and recommended moving forward into the construction phase.
Commissioners asked for clarification about the contract total. The presenter confirmed the amended contract total would be $1,503,500 including pre-construction services. Following a motion and second, the board voted to approve the guaranteed contract amendment, enabling Sunbelt Builders to proceed to construction planning and procurement under the GMP.
The county will oversee usual construction-phase reporting and will return to the board with any change orders or scope adjustments that exceed the GMP.