Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
Design revision adds $69,500 to Riverchase Village drainage project, ALDOT permit paused schedule
Summary
An ALDOT design revision for a drainage structure required additional reinforcement and concrete, producing a $69,500 change order that remains on budget; the contractor has 150 calendar days to complete the work once the change order is approved and materials are ordered.
Get email alerts on the Drainage topic
No spam. Unsubscribe anytime.
City staff told council that during the ALDOT permitting process a design revision was required for a drainage structure in the ALDOT right‑of‑way for the Riverchase Village project.
Mister Marlin said the revised design included additional reinforcement and concrete and that the resulting change order of $69,500 "still puts us well on the budget." He explained that time under contract was paused while permits were processed and that if the change order is approved the contractor will order materials and begin work, with 150 calendar days to complete the project.
Council members asked about the project timeline and any design implications. Staff said they expected the contractor to start within about two weeks after approval and ordering of materials. The change order was introduced as Resolution No. 871826 in the work session; no formal vote was recorded there.

