Breckenridge council approves $279,698.95 change order for street improvement phase 3

Breckenridge City Council (unnamed meeting) · January 5, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved change order #1 for street improvement phase 3 to add work and address unforeseen conditions, increasing contract time from 120 to 150 days and raising the contract price by $279,698.95.

The Breckenridge council approved Change Order #1 for street improvement Phase 3, adding scope and addressing unforeseen utility conflicts and pavement issues.

City Manager (Speaker 4) explained the change order includes quantity adjustments, conversion to concrete pavement at the West Williams Street and Shelton intersection, added work on Oakwood and Northglenn Street and replacement of a shallow water line at Second and North Miller. He said the contract time will increase from 120 to 150 days and the contract amount will increase by $279,698.95. "We folded it into this contract... the contract amount by $279,698.95," said Speaker 4.

Speaker 1 moved to approve the change order and Speaker 2 seconded; the council approved the adjustment by voice vote.

Staff said the change order remains under the 25% increase threshold from the original contract maximum and the work is integrated into ongoing Phase 3 construction.