Ballston Spa board awards $1.21 million attic/HVAC contract for library

Village of Ballston Spa Board of Trustees · January 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved a $1,212,029.70 contract with Wayne Shaft Associates Inc. to install attic/HVAC work at the Ballston Spa Public Library; mayor said the company was the lowest of three bidders and the board hopes work will begin Monday.

The Village of Ballston Spa Board of Trustees on Jan. 1 approved a $1,212,029.70 contract with Wayne Shaft Associates Inc. for attic installation and associated HVAC work at the Ballston Spa Public Library.

Mayor explained the board solicited three bids and that Wayne Shaft was the lowest of the three. "They were the lowest bid of 3 that we did check," the mayor said during the discussion, adding that the village was "hoping to get in there on Monday" and that staff were taking measures (space heaters, running faucets) to protect the building during the work.

Trustees affirmed the procurement process during the vote and authorized the mayor to execute any relevant paperwork to move the project forward. The mayor and engineering staff thanked contractor contacts and engineers who expedited the procurement.

The board noted contingency planning for cold weather during installation and that the village followed a three‑bid review process for this price range.

Next steps: authorization for the mayor to sign contract documents and coordination with engineers and library staff on the project start date and protective measures during construction.