Lee County broadband projects on track, officials say; several segments set to finish in 2026

Lee County Commission · November 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County broadband coordinator reported progress across multiple federally funded fiber projects — Salem (complete), several South Central and Phase 2 areas now in permitting or construction, and a Lo Chipoca project due January 2026 — and agreed to provide regular updates on Spectrum activity.

Miss Leverett, the county broadband project coordinator, told the Lee County Commission that the county’s federally funded fiber build is advancing across multiple project areas and that several segments are scheduled to finish well before the federal reporting deadline.

"The Salem project...is 8.5 total fiber miles, with a total served of 110 locations," Leverett said, and noted the Salem work was "100% complete as of December". She said a separate Phase 1 South Central contract awarded to RM Green covers 11.1 fiber miles serving 187 locations and is in…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans