Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the City It Projects topic

No spam. Unsubscribe anytime.

IT director seeks acceptance of Genetec access control project and release of retainage

City of Pasco City Council (Workshop) · January 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

IT Director Arman Rashid asked the council to accept the Genetec citywide card and access project performed by Inner West and to release retained funds; staff said the original 2023 authorization was $460,000, installed work totaled $396,000 and retainage to be released is $14,088.92.

Arman Rashid, the city’s IT director, briefed the council on the Genetec unified security project and recommended acceptance of work performed by Inner West Technologies (contract name in packet) and release of the retainage.

Rashid said Council previously approved a resolution on July 17, 2023 authorizing $460,000 for the Genetec Unified Security System contract. Installed sites listed included City Hall, multiple fire stations and Pasco water treatment plants, with installed costs totaling about $396,000, leaving the project under budget. Staff recommended acceptance and the release of retainage held by the city in the amount of $14,088.92. Council confirmed the expenditure was part of the capital improvement program and had been budgeted as a capital project.

No public comment or additional questions were offered beyond routine confirmation of the funding source and the project timeline.