Land Use Review Board urges digitization and seeks extension of Act 250 jurisdictional authority

Committee on Commerce & Economic Development · January 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Land Use Review Board told the committee that digitization and staffing are needed to improve public access and permitting efficiency; the board reported issuing 350–400 permits annually, about 270 jurisdictional opinions, and said only 0.2% of hearings-level permits were denied. It recommended extending certain jurisdictional authorities to Sept. 30, 2026.

The Land Use Review Board described modernization steps and requested an extension of certain jurisdictional authorities under Act 250 during a joint hearing reported to the Committee on Commerce & Economic Development on Jan. 9.

"They have around, like, 550 boxes of paper files," Bailey Davis, a committee intern from Norwich, said summarizing the board’s testimony on digitization and public access.

Davis reported that the board handles roughly 350–400 permits a year and issues about 270 jurisdictional opinions; testimony cited a denial rate at the board level of approximately 0.2% (about five to ten permits). The board said digitizing case files would improve public access and staff efficiency and asked to hire two permanent district coordinators to expand permitting capacity.

On policy specifics, Davis explained Act 250’s tier structure: Tier 1a provides a full exemption, Tier 1b offers partial exemptions for housing projects of 50 units or fewer on 10 or fewer acres in designated growth areas, and tier 2 areas face different permitting considerations. The Land Use Review Board described proposed statutory and rule changes, additional guidance and fact sheets for particular industries (notably wood-product manufacturers), and creation of a permit specialist role.

The board also said it seeks an extension of its jurisdictional authority to Sept. 30, 2026, for some tier 2 areas and noted use of ARPA funds for about 100 permits this year, 16 of which were directly related to housing projects.

Why it matters: Act 250 remains the state’s primary land-use permitting framework. The board framed digitization and modest staffing increases as measures to make past permitting history accessible to developers and the public and to reduce administrative bottlenecks.

Next steps: Committee members asked about average permit timelines; the testimony did not provide dates or average processing times, and interns offered to follow up for additional operational detail.