Lighting project moves through INDOT environmental review; Avitec sewer 30% complete
Sellersburg Redevelopment Commission · January 6, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
JTL reported the camper-and-lighting project has submitted environmental documents to INDOT and is awaiting approval; Avitec’s sewer installation is about 30% complete with roughly 1,400 feet of 4,900 planned installed. No INDOT approvals or opening dates (Wawa) were provided.
Josh, representing JTL, told the Sellersburg Redevelopment Commission that the camper-and-lighting project remains in the environmental-review phase and that SJCA has submitted all required environmental documents to the Indiana Department of Transportation…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans