New Hoke County high school nearing finish; substantial completion targeted spring 2026
Summary
Contractor reported the new high school is roughly 78% complete with windows, labs, cafeteria and learning stairs in place. Substantial completion is targeted for April–May 2026, final completion May–June, and occupancy and move‑in activities planned for summer with contingencies remaining in the project budget.
Board members received a construction update on Jan. 13 showing steady progress at the new high school and a schedule that keeps the district on track for fall occupancy.
The construction presenter (Speaker 10) displayed photos showing the main entry, two‑story classroom wings, cafeteria and the learning stairs/media center in place. The presenter said windows are installed — a milestone for interior work — and that the science labs and…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat