Public Works outlines bridge, storm-drain and on-call contracts; Allender Road bridge bid near $1.6 million
Summary
Public Works presented consent items including a call for bids, a personal services agreement for stormwater (Gray & Osborne, NTE $120,000), an on-call electrical contract for the landfill (Advanced Electrical Technologies, NTE $150,000), and an Allender Road bridge low bid around $1.6 million funded entirely by federal bridge funds.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Susan Eugenis, county engineer, summarized Public Works’ consent agenda items for the next meeting, highlighting procurement and construction work for winter-to-spring mobilization.
Eugenis said the county will issue annual calls for bids for culvert pipe and drainage supplies and reported the contract-execution paperwork for the Allender Road bridge project is forthcoming. She said the project received 13 bids and that the lowest bid was approximately $1,600,000; the project is funded entirely with federal bridge funds. Eugenis said she expects to have the contract ready for execution the next day and that the contractor will mobilize and attend a preconstruction meeting before in-water work; she noted a 200-working-day contract and in-water fish-window timing for some activities. Eugenis said a temporary bridge will be installed before removing the old bridge so no residents will become landlocked.
Eugenis also described a personal services agreement with Gray & Osborne to support the municipal separate stormwater (MS4/MPDES) permit through Dec. 31, 2028, not to exceed $120,000; the county used a qualifications-based selection process and conducted interviews. Sean, finance director, noted a final contract execution for Advanced Electrical Technologies for on-call electrical services at the Headquarters Landfill: not to exceed $150,000 for one year with an option to extend one additional year.
Eugenis said the county is completing paperwork to rescind an emergency declaration and issue a completion letter to Advanced Excavating Specialists for storm-drain replacement work on Sweet Birch; total cost was reported as $141,988.85. She said the contractor mobilized and work is complete with paperwork being finalized.
Eugenis answered commissioners’ questions about schedule and fish-window constraints and said contractors will begin preparatory work before the date they may touch the water. No public votes or formal approvals are recorded in the public segment of the transcript.