Castle Park play structure replacement gets funding, volunteer build set for April
Summary
Council approved two contracts and Measure A appropriations for the Castle Park play-structure replacement; a community volunteer build is scheduled for April 7–12, and site work will address ADA access and stub utilities for a future restroom.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The City Council approved two resolutions authorizing construction agreements and funding for the Castle Park Place play-structure replacement project, and staff announced a volunteer build scheduled for April 7–12.
Park planner Hannah Perez presented the project scope: site clearing and grading before the community build, demolition and replacement of an ADA-noncompliant sidewalk segment along Pruitt Drive, stubbed electrical and potable-water utilities for a future restroom, and post-build installation of engineered safety surfacing. Granite Construction agreed to perform the concrete pavement work and donate half the concrete; KYA is proposed for site work and safety-surfacing installation via a cooperative purchasing agreement (CMAS).
Projected project totals were presented: design subtotal $158,835, playground materials $379,438, construction subtotal $462,169 for a project total of about $1,001,229 including contingency. Funding breakdown includes $800,000 in parks and recreation equipment/capital funds (projected spend $716,063), a Measure A appropriation request of $135,201, and nonprofit/donation support via Folsom Kids Play for Generations for about $149,965.
Council members praised inclusion of utilities stub for a future restroom and the collaborative funding approach. Staff said the play structure build will be community-led with many volunteer shifts already signed; final safety surfacing and punch-list work will continue after the community build, with a target to open by the end of April.
Two resolutions authorizing contracts with Granite Construction (concrete work, not to exceed $72,356; Measure A appropriation $79,529 including contingency) and KYA (site work, not to exceed $308,309) were moved, seconded, and approved by roll call.